Year 2023
Nation Italy
Client Tecnic S.r.l.
Structure type Bridges and infrastructures
Activity performed Detailed design
Project value 594 000 000 €
Key works Construction of a new double-track railway line (partly on a new route, partly alongside existing track)
Decommissioning of the current single-track section
Elimination of level crossings
Electrification of the new line
Civil and structural works, including bridges and underpasses
Environmental mitigation and landscape integration measures
Upgrading of Termoli and Ripalta station areas